Civil Works
- Owner : MPW
- Year : 2018
Civil Works
Contract No: | Activities | Company |
---|---|---|
SO-0146/05 | Construction of Septic tank 6.6 X 3.5m & Flooring Plumbing Works | Al-ghanim |
GP/LP/05/0466 | Piping work at compressor area | ABC |
SO-192/05 | Concrete paving work & new site office | Al-ghanim |
GP/LP/05/00720 | Unloading, Rigging & Erection of Equipment | ABC |
AGECO/102/05 | External Plastering work at rotana | AGECO |
GP/LP/05/00720 | Unloading, Rigging, & Erection of Equipment | ABC |
Concrete flooring work for electrical & fabrication room | Muntaser | |
GP/LP/06/00141 | Sewage piping work pump erection, welding & fabrication of support | ABC |
Installation of Chain link fence including Auguring & concrete poring | Mushrif | |
Scaffolding arrangement of barrisol fixation Avenue project | Mustaser | |
SC/RA51.2006/002 | Casting of Blind concrete, RC Manhole, Gullies, Precast Manholes, Steps/Ladders | Mushrif |
SC/RA-34/2005 | Overhead sign Gantry Pole foundation work | Mushrif |
A101201 | Execution of Electrical work at IHED Workshop | ISCO |
Fire fighting work at Al-Manshar Project | Gulf.Engg | |
FF-01 | Fire fighting work at Rotana Hotels | Gulf.Engg |
POG/KVAC/127 | Ducting work for HVAC replacement project | Primeone |
GP/LP/06/0716 | Electrical power cabling works at combiloc | ABC |
GP/LP/06/00889 | Unloading of container and shifting to the location | ABC |
Contract No: | Activities | Company |
---|---|---|
GP/LP/07-08 | Electrical work for combiloc machine line-6 | ABC |
JO/SC-40/GS-02 | Field maintenance support services excavation works | SMS |
Fire fighting work at Jaber-Al-Jaber stadium | Kharafi | |
AS-07-096-PO-001 | Structural fencing work at Al-Kout food factory Subhan | Al-ghanim Sepam |
RA-34 Civil works including Manhole,Foundation, Lighting pole foundation | Mushrif | |
Internal wall plastering work at Al-Kout | Al-ghanim Sepam | |
1350/A/010/001-08 | Installation of cable trunking and cable trays | Kharafi |
Construction of Boundary wall | Al-ghanim Spem | |
Demolition of stall Astra Refrigeration unit & Ice Tank | ABC | |
TER-CNS-300 | New Airport Terminal Building Excavation Works | |
TER-CNS-312 | New Airport Terminal Retailing Wall Concrete | |
New Airport Terminal Clearing & Grubbing | ||
TEF-CNS-303 | New Airport Terminal Precast Factory Foundation |